. Design of the” Rainfall Drainage Network for the National Capital(Khartoum, Omdurman & Khartoum North )”,
Consulting Firm : Agib-Howard Humpherys Joint Venture, 1991
Client: Ministry of Engineering Affairs, Khartoum State
2. Design of the” Drainage Structures for El-Renk – Malakal Road “, (330 km) ,1997
Consulting Firm : Stippe-Techncon Joint Venture
Client: Ministry of Highways & Transportation
Consulting Firm : Techncon
Client: Ministry of Highways & Transportation
4. Design ,in participation with other colleagues, of the” Drainage Structures for En Nuhud-Rigl elFula-ElMuglad Road “, (230 km), as a consultant for University of Khartoum Consultancy Corporation ,1998
Client: Ministry of Highways & Transportation
5. Design of the” Rainfall Drainage Network for Singa town”, as a consultant for El-Dar El-Estisharia
Client: Ministry of Engineering Affairs, El-Gadarif State
Tama Irrigation Scheme :This is a 6000 Feddan scheme on the Blue
Nile near Karkooj (Blue Nile State), 1992
Client: Ministry of Engineering Affairs, Sennar State
Client: Khartoum University
Client: Sanabil Cooperative Committee
Consulting Firm : University of Khartoum Consultancy Corporation.
Client: Merowe Dam Project ImplementationUnit,1999.
Consulting Firm : University of Khartoum Consultancy Corporation.
Client: Merowe Dam Project ImplementationUnit, 2000.
Consulting Firm :University of Khartoum Consultancy Corporation
Client: Merowe Dam Project ImplementationUnit ,2003.
Consulting Firm : University of Khartoum Consultancy Corporation.
Client: Merowe Dam Project ImplementationUnit, 2005.
i) design of a 66 km long pipeline with a pump station
ii) design of a water reservoir at the outfall of a small stream
iii) design of an earth dam with deep sluices and a spillway
Client: Ministry of Engineering Affairs, El-Gadarif State
Client: Ministry of Engineering Affairs, South Darfur State
15. Development, in participation with other colleagues, of “ Ground Water Mathematical Model for El-Gadarif Aquifers” ,(1997)
Client: Ministry of Engineering Affairs, El-Gadarif State
16. Design, in participation with other colleagues, of “ Wadi Gabatit
(Red Sea State) Water Supply Scheme”,(1997) , which inculde the
following :
i) design of a 15 km long pipeline
ii) design of an underground dam
iii) design of an earth dam with a spillway
Client: Ministry of Engineering Affairs, Red Sea State
17. Design, in participation with other colleagues, of “ Wadi Moj (Red Sea State) Water Supply Scheme”,(1999) , which include the following :
i) design of a 12 km long pipeline
ii) design of an earth dam with a spillway
Client: Ministry of Engineering Affairs, Red Sea State
18. Design,in participation with other colleagues, of “ Sudd El-Daiga (Khartoum State) Water Supply Scheme”,(1999) , which inculdes
the design of an earth dam with a spillway
Consulting Firm : University of Khartoum Consultancy Corporation.
Client: Ministry of Engineering Affairs, Khartoum State
19. Design, in participation with other colleagues, of “ Wadi El-Mugadam (Khartoum State) Water Harvesting Scheme”,(1999) , which inculdes the design of an earth dam with a spillway
Consulting Firm : University of Khartoum Consultancy Corporation.
Client: Ministry of Engineering Affairs, Khartoum State
20. Design ,in participation with other colleagues, of the Canalization System, Drainage System, Irrigation structures and Pump Stations of “The Bioremediation Project”, at Hegleig Oil Field, 2000.
Consulting Firm : Solar Enterprises Company
Client: Greater Nile Petroleum Operating Company
21. Supervision of Construction of the Canalization System, Drainage System, Irrigation structures and Pump Stations of ElMultaga Scheme: This is a 15000 feddan scheme on the eastern bank of the Blue Nile near ElDaba (Northern State), 2002.
Consulting Firm : University of Khartoum Consultancy Corporation.
Client: Merowe Dam Project ImplementationUnit.
22. Design ,in participation with other colleagues, of the Evaporation Ponds ,Canalization System, Drainage System, at Bamboo, Toma South, ElToor, ElHar-ElNar, Munga and Unity Oil Fields, 2002.
Consulting Firm : Solar Enterprises Company
Client: Greater Nile Petroleum Operating Company
23. Design ,in participation with other colleagues, of the Evaporation Ponds ,Canalization System, Drainage System, at Khartoum Refinery, 2002.
Consulting Firm : Techneco Group
Client: Khartoum Refinery
24. Project Manager for the Supervision of Construction of the Canalization System, Drainage System, Irrigation structures and Pump Stations of New Amri Scheme: This is a 35000 feddans scheme on the eastern bank of the River Nile near Korti (Northern State), 2004-2007.
Consulting Firm : University of Khartoum Consultancy Corporation.
Client: Dams ImplementationUnit.
25. Supervision of Construction of the Canalization System, Drainage System, Irrigation structures and Pump Stations of AlMokabrab Scheme: This is a 60000 feddans scheme on the eastern bank of the River Nile near AlDamer (Nile State), 2004-2007.
Consulting Firm : University of Khartoum Consultancy Corporation.
Client: : Dams ImplementationUnit.
26. Supervision of Construction of the Canalization System, Drainage System, Irrigation structures and Pump Stations of Kehaila Scheme: This is a 45000 feddans scheme on the eastern bank of the River Nile near Abu Hamad (Nile State), 2006-2008.
Consulting Firm : University of Khartoum Consultancy Corporation.
Client: Dams ImplementationUnit.
27. Hydraulic Design of the” Drainage Structures for Kadogli-Lagawa- AlFoola Road “, (170 km), 2006
Consulting Firm : Techno Group
Client: Ministry of Highways & Transportation
28. Hydraulic Design of the” Drainage Structures for Kadugli – Higlieg Road with a length of 130 km and Mujlad – Abyei Road with a length of 220 km, 2009
Consulting Firm : Shouraconsult Company Ltd
Client: Ministry of Highways & Transportation
29. Team Leader for the “ Technical & Financial Feasibility Study of Al-Roseiris Irrigation Scheme”: This is a 200,000 feddans scheme on the eastern bank of the Blue Nile near Al-Roseiris (Blue Nile State), 2009.
Consulting Firm : University of Khartoum Consultancy Corporation.
Client: Dams ImplementationUnit.
30. “Water Resources Assessment (WRA) in Southern Sudan”, 2010.
Consulting Firm : University of Khartoum Consultancy Corporation.
Client: Government of South Sudan.
31. Team Leader for the “ Technical & Financial Feasibility Study of Al-Shereik Irrigation Scheme”: This is a 40,000 feddans scheme on the eastern bank of the River Nile near Al-Sherik ( Nile State), 2010.
Consulting Firm : University of Khartoum Consultancy Corporation.
Client: Dams ImplementationUnit
32. Team Leader for the” Design of the Drainage Structures for Baleela-Um Adara Road “, (98 km), 2012
Consulting Firm : University of Khartoum Consultancy Corporation.
Client: Petro-Energy Company
33. Team Leader for the” Design of the Drainage Structures for For Block 6 (Jake-Keyi-Sentaya and Muglad) “, (84 km), 2013
Consulting Firm : University of Khartoum Consultancy Corporation.
Client: Petro-Energy Company
34. Project Manager for the Supervision of Construction of the
” Drainage Structures for Baleela-Um Adara Road (Shalango Sector)”, EPCC Contractor: Sudan Pile -Jobdeliver, 2014-2015
Consulting Firm : University of Khartoum Consultancy Corporation.
Client: Petro-Energy Company
35. Project Manager for the Supervision of Construction of the
” Drainage Structures for Jake-Keyi-Sentaya and Muglad “,
EPCC Contractor: Shandong, 2015.
Consulting Firm : University of Khartoum Consultancy Corporation.
Client: Petro-Energy Company
36. Team Leader for the “ Technical & Financial Assessment Study of The Existing Irrigation 58 Schemes in Northern State, Nile State & Sennar State”: Total Area is 657,000, 2015.
Consulting Firm : University of Khartoum Consultancy Corporation.
Client: Ministry of Finance
37. Hydrologic and Hydraulic Design of the” Drainage Structures in Delta Toker Scheme, Red Sea State”, 2015
Consulting Firm : University of Khartoum Consultancy
Client: Eastern Sudan Rehabilitation and Development Fund